Conveyance Project

Conveyance Project construction began in November 2018, with Project completion anticipated late 2020.

If you would like to sign up to receive Project updates, please contact the Community Liaison Officer by phone at 778-382-9011 or by email at [email protected].

Conveyance Project Updates

Starting late March 2019, work on West 1st Street will begin to connect the new North Shore Wastewater Treatment Plant to the existing outfall, and the new plant to the existing sewer system.

First Narrows Pump Station

Installation of Outfall Pipe: March 2019 – April 2020

The Project will use a combination of microtunneling, slip-lining, and open cut techniques. Microtunneling and slip-lining use a limited number of above-ground access points (shafts/trenches/etc.) to limit surface impacts.

  • Microtunneling is a self-contained system which reduces noise, dust and impacts to the environment and travelling public.
  • To prepare the staging areas, secant piles (drilling holes and then filling the holes with cement to strengthen the ground) will be installed.
  • This method of ground improvement limits noise, while still creating the watertight structure required for microtunneling.

Pipe Alignment

Installation of Sewer Pipe: July 2019 – Sept 2019

The Project will use open cut installation for this component (locations C and D on map below).

  • Work will be completed in sections to minimize disruptions. Microtunneling is not suitable for this component as the pipe is smaller in diameter and there are many utilities in the area and connections are required.
  • Crews will remove sections of asphalt, lay down and connect the pipe, and replace the asphalt.

All activities will take place during regular work hours of 7 am to 8 pm Monday to Friday, and 9 am to 5 pm on Saturday. No work will take place on Sundays or statutory holidays. Access to local business will be maintained.

Temporary lane closures

Please see map below.

A) Eastbound West 1st Street west of Philip Ave. (March 2019 – April 2020)

  • One lane of traffic will be maintained in each direction
  • Pedestrians may be detoured to the south side of West 1st St.
  • Cyclists will share the road with vehicles

B) Eastbound West 1st Street west of Garden Ave (March 2019 – April 2020)

  • Local access only to this no exit block

C) North Frontage Lane (July 2019 – Sept 2019)

  • Alternate access to local businesses from Welch St. via Garden Ave. and Philip Ave.
  • Temporarily close north parking lane and bicycle lane – cyclists will share the road with vehicles.

D) & E) Full Closure of the intersection of Garden Ave. at West 1st St. to install pipes (July 2019 – Sept 2019)

  • Detour for cyclists and vehicles via Philip Ave. and Welch St.
  • Access to local businesses will be maintained

Project Overview

The Lions Gate Wastewater Treatment Plant, situated just to the west of the Lions Gate Bridge, serves the North Shore municipalities of West Vancouver, the City of North Vancouver, the District of North Vancouver, and Squamish Nation. The plant is one of two remaining primary treatment plants in the region.

New federal regulations require all primary treatment plants be upgraded to secondary treatment by December 31, 2020. Secondary treatment is a biological process that uses aerobic bacteria to consume suspended solids and dissolved organic materials in wastewater. Secondary treatment plants remove about 95 per cent of the organic materials in wastewater. The new facility will provide a higher level of treatment to the North Shore’s wastewater before it is sent into Burrard Inlet.

In July 2018, Metro Vancouver awarded the North Shore Conveyance Partners (NSCP) the contract to design and construct a pump station and related pipes to convey wastewater from the existing Lions Gate Wastewater Treatment Plant to the new North Shore Wastewater Treatment Plant  that is currently under construction on West 1st Street between Pemberton Avenue and Philip Avenue.

The new First Narrows Pump Station will be located near the existing Lions Gate Wastewater Treatment Plant. The pipe alignment will extend from the existing outfall under the Lions Gate Bridge to the new North Shore Wastewater Treatment Plant. The Conveyance Project includes the following components:

  • Constructing a new pump station located at south end of Bridge Road underneath the Lions Gate Bridge
  • Installing a 1200 mm influent sewer pipe extending from the existing Lions Gate Wastewater Treatment Plant to the new pump station
  • Installing a 900 mm forcemain extending from the new pump station to the new North Shore Wastewater Treatment Plant
  • Installing a 2100 mm effluent sewer pipe extending from the new North Shore Wastewater Treatment Plant to the existing outfall

With plant construction underway, the Conveyance Project represents the next step in the overall North Shore Wastewater Treatment Plant program. The final step, decommissioning the existing Lions Gate Wastewater Treatment Plant, will begin in 2022/2023 and the land returned to Squamish Nation.

To review the permit application with the Vancouver Fraser Port Authority, visit here.

Infrastructure Map

Engagement Overview

A public open house was held on October 25, 2018 and the feedback period on construction mitigation is closed. See the Open House Display Boards for project information.

 Conveyance Project Engagement Summary – Jan 2019